Government of Nepal
Ministry of Energy, Water Resources and Irrigation
Department of Water Resources and Irrigation
Sikta Irrigation Project
Nepalgunj, Banke
A brief introduction
A barrage of length
317 m has been constructed on the Rapti River at Agaiya of Rapti Sonari Rural
Municipality in Banke District of Lumbini Province with the aim of providing
reliable irrigation facilities on total 42,766 hectares of land of 6 rural municipalities,
Kohalpur municipality and Nepalgunj sub-metropolitan of same district. The
Sikta Irrigation Project, which was started from F.Y.2062/63 by the Government
of Nepal from its own resources, covers command area 33766 hectares on the
western side and 9000 hectares on the eastern side of the Rapti River.
Background
Initially, the
concept of Sikta Irrigation Project was proposed as West Rapti Multipurpose
Project mentioned in the Pre-Feasibility Study (AD 1975 to AD1976).
Pre-feasibility study of Sikta Irrigation Project was done in BS 2032 (AD 1975)
by German consulting firm with the help of UNDP and ADB, the feasibility study
report of this project was submitted in BS 2036 (AD 1980) by the same
organization. From this study, the project was found to be feasible and
requested Asian Development Bank for financial assistance to implement the
project in 2036. Since the Indian side could not provide the consent over
implementation of this project, the Asian Development Bank expressed its
inability to provide financial assistance, so the implementation of this
project could not proceed.
The re-feasibility
study of this project was done in BS 2040 (AD 1983) by the Regional Irrigation
Directorate under the Department of Irrigation, Environment and Meteorology,
while the feasibility study of this project with the financial support of the European
Union was last done in BS 2059 (AD 2002). The study completed with the
participation of European engineers, it was recommended to implement the
project as it was seen to be feasible from the technical and financial aspects.
According to the feasibility study, the total cost of this project was
estimated 7 billion 45 crores at that time. The implementation period of the
Project was kept for seven years.
When the project
looked attractive, the European Union, Saudi Fund for Development (SFD), Kuwait
Fund for Arab Economic Development and OPEC Fund were requested to provide
financial support for the implementation of project and these donor
organizations shown their interest. For the construction of the project costing
about 100 million US dollars, after the above-mentioned organizations had
divided among themselves who would support how much money, due to various
reasons, this project was again deprived of the opportunity to receive the
support of donor organizations.
As external financial
assistance was not available, the only option to provide irrigation facilities
in the dry land of Banke was to provide funds from internal sources for the
implementation of Sikta Irrigation Project. According to this, the Irrigation
Department proceeded with the contract management of the construction process
of the main dam and main canal with the financial and technical resources of
the Government of Nepal.
The procurement
master plan of this multiyear project was approved (Rs. 12 billion 80 crores)
on BS 2064/8/3 to be completed by F.Y.2070/071. In the Procurement Master Plan,
it is envisioned that the project will be completed in three phases, but only
12.8 billion is estimated for the first and second phase and the cost of the
third phase is not included. Again, with the target of completion of
project in F.Y.2076/77 (15 years) revised procurement master plan of 25 billion
2 crores was prepared which includes additional 9000 hectares of command area
on eastern side by constructing eastern main canal and other structures. It
seems to have been approved in F.Y.2071/72.
Since the project was
not achieved the target mentioned in the approved latest procurement master
plan to complete the entire work by F.Y.2076/77, the directive/decision to
re-submit the proposal for time extension of the updated procurement master
plan within the same cost. At the end of F.Y. 2078/079, the cost estimate
revised and master plan updated with the DPR report accounting of the progress
of the construction works and the remaining works to be done in the future is
Rs. 52.64 billion to complete total works by F.Y.2089/90 and has been approved
on 2079 Bhadra by the Ministry of Energy, Water Resources and Irrigation under
rule 7 of the Public Procurement Regulations 2064.
17thousand householders in the district of 4 lakh
farmers are expected to benefit from the project, and the estimated internal
return of the project is 18 percent with increasing crop
density 168 percent to 242 percent.
The main works
completed under the project so far:
1. Headworks (Civil
and Hydro mechanical works)
2. West Main Canal
(45.25 km)
3. Land acquisition
(110.55 ha.)
4. West Main Canal
with 4 branches (Akalgharwa 4.6 km, Gohwa 2.05 km, Prasenipur 4.6 km and Pidari
4.1 km)
Works under
construction for this fiscal year 2079/080:
1.
Shidhaniya branch (5.2 km to 6.0 km under construction) to be completed in
current fiscal year
2.
East Main Canal (started in F.Y.2074/75) from the said contract, main canal
with concrete structure up to 37+675 chainage and earthen canal up to chainage
44+900, and branch canal (Rajkulo, S1, S2, S3, S4 and Phattepur) will be
completed in month of February of current fiscal year.
3.
Command area protection works (ongoing at some places)
4.
Environmental Impact Assessment and Prevention works
5.
Land Acquisition (Main Canal, Branch and Branch
Canals) etc.