क्र.सं | ठेक्का नम्बर | ठेक्का को कामको विवरण | निर्माण ब्यबसायीको नाम | ठेक्का सम्झौता रकम (रु) भ्याट सहित | सम्झौता मिति | ठेक्का अवधि | कैफियत |
---|---|---|---|---|---|---|---|
1 | SIP/077-78/works/NCB-03 | Rehabilitation and Protection works of Sikta Main Canal | M/S PUSHPANJALI-P.S. JV | ||||
2 | SIP/077-78/goods/NCB-01 | Supply of tools and parts of Sikta Headworks at Agaiya | M/S SAURAV CONSTRUCTION | ||||
3 | SIP/GOODS/LAB/SQ-02/078-79 | Supply and Delivery of Laboratory Equipment and Materials | M/S International Science House Pvt. Ltd. | ||||
4 | SIP/RSC/NCB-05/078-79 | Construction of RCC Slab Culvert at Chatar,Dunduwa Branch | M/S Maurya R.S. Nirman Sewa | ||||
5 | SIP/HPC/NCB-06/078-79 | 'Hume Pipe Crossing at chainage 37+697 & 35+284 | M/S Kaji and Brothers Builders Pvt. Ltd. | ||||
6 | SIP/RMHW/NCB-04/078-79 | Repair and maintenance of headworks, settling basin, escape and nearby structures | M/S Grow Up Construction & Builders Pvt. Ltd. | ||||
7 | SIP/MGH/SQ-01/078-79 | Construction Of Moranga Guard House at Rapti Sonari Rural Municipality-04, Moranga, Banke | M/S Bhawar Bhawani Nirman Sewa | ||||
8 | SIP/CAP/GPW/NCB-02/078-79 | Command Area Protection Work at L/s of Dunduwa Khola | M/S P.S.Nirman Sewa | ||||
9 | SIP/CAP/KPW/NCB-03/078-79 | Command Area Protection Works of Kiran Nala D-Gaun Shirjana Tol & D/S of Gohawa Escape | M/S P.S.Nirman Sewa | ||||
10 | SIP/CAP/GBPW/NCB-01/078-79 | GallaBaj Protection works with Spur and launching including extension of existing spur | M/S Oli Builders | ||||
11 | SIP/077-78/works/NCB-03 | Rehabilitation and Protection works of Sikta Main Canal | M/S PUSHPANJALI-P.S. JV | ||||
12 | SIP/CAP/NCB-16 | Command Area Protection Work at Rapti River 2700m Downstream from Sidhaniya Ghat Bridge | M/S DEV & SAYAR / MALLA JV | ||||
13 | SIP/SBC/NCB-04 | Construction of Canal and Structure of Sidhaniya Branch Canal (Ch. 5+200 to 6+000) | M/S Amar/Majdoor Jv | ||||
14 | SIP/EMC/ICB-01 | Construction of Eastern Main canal, Rajkulo & Fattepur Irrigation system | M/S Kalika & Kumar JV |